Bulk Management Project’s

Bulk Management (Pvt.) Limited

Ground Improvement for Warehouse in Port Qasim of Bulk Management Pvt Ltd.

Strength Comparison

EXISITNG
IMPROVED
55 kPa
120 kPa

The Bearing Capacity achieved was approximately 118% more than existing strength after Ground Improvement using Vibro replacement via 716 Stone columns with a 2.2 improvement factor

INCREASE

2.18x

Untitled design 53